18th Street and University Avenue Intersection

PW Project Update-InstaWater main work and the re-installation of street lights is being finished at the intersection of 18th Street and University Avenue.

However, the intersection will remain closed through the weekend as it is currently being prepped for pavement work which is scheduled to begin Tuesday, August 4.

The paving process takes about 2 days to complete.

The intersection will reopen by next Friday, August 7 barring any extreme weather delays.

To view ongoing construction areas, please visit the 2020 Construction Map: https://bit.ly/Construction2020